Project Gallery

Project: Concrete Floor - New Asda Store Strabane

 
JobConcrete floor in a new Asda store in Strabane
Main ContractorGilbert Ash
Concrete SupplierJ Barrett & Sons
Flooring ContractorM R Concrete
DescriptionThe concrete was placed in one continuous pour of approximately 1200 cubic metres in a 12 hour period. To create an easily placed and finished concrete, Chemcrete HP3 was added to the concrete to increase slump without increasing the water content. As a further measure to reduce drying shrinkage cracking, the floor was sprayed with Larcure ST curing membrane.
  • 05. Spraying Curing Membrane

    05. Spraying Curing Membrane

  • 04. Finishing Concrete

    04. Finishing Concrete

  • 03. Concrete Placing

    03. Concrete Placing

  • 02. Concrete Pump

    02. Concrete Pump

  • 01. Delivery

    01. Delivery